Finished bunker complex and green at Fantasy Valley Golf Course, an Aspen golf course construction project at Wisp Resort

GOLF COURSE CONSTRUCTION · SINCE 1982

Replacing Four Holes and Protecting a Trout Stream With Expert Golf Course Construction

When a real estate development took four holes out of play at Wisp Resort’s Fantasy Valley Golf Course, Aspen built four new ones to take their place — integrating them seamlessly into the existing 18-hole layout while protecting Hoyes Run, one of Maryland’s most sensitive trout streams, just steps away. See how we turned the challenge into a fantasy come true at Fantasy Valley.

Finished bunker complex and green at Fantasy Valley Golf Course, a second angle, after golf course construction
FEATURED CASE STUDY

44 Years +

Years of golf course construction

GCBAA

Certified Builder · Charter Member

2009

Golf Course Industry Affinity Award Winner

PROJECT SNAPSHOT

Fantasy Valley Golf Course · McHenry, Maryland

TYPE OF PROJECT

Renovation — 4 New Holes

PROJECT VALUE

More than $1.5 million

TIMELINE

July 2006 – June 2008

GOLF ARCHITECT

Todd Schoeder, Design Workshop

BUILDER

Aspen Corporation

COURSE SUPERINTENDENT

Scott McMillion

OWNER REPRESENTATIVE

Steve Richards, DC Development, LLC

RECOGNITION

2009 Golf Course Industry Affinity Award

THE PROJECT

At Wisp Resort, Aspen constructed four brand-new holes and wove them into the existing 18-hole Fantasy Valley Golf Course — replacing four holes taken out of play for a real estate development, without the course ever losing its rhythm.

The site required an extensive erosion and sediment control plan, approved by the Maryland Department of the Environment, to protect Hoyes Run — one of Maryland’s few Class Tier II trout streams and one of the most sensitive waterways in the state. Aspen and Design Workshop architect Todd Schoeder built in additional protections beyond what was required.

This was the first golf course work ever permitted in Garrett County with the Department of the Environment, and the unfamiliar process brought delays. Aspen built more than 22 sediment basins across the four new holes and installed extensive super silt fencing, adjusting grades on some basins multiple times to keep them functioning as both erosion control and finished sub-grade.

The property had previously been developed as a theme town called “German Village at Fantasy Valley.” Before construction could begin, Aspen coordinated the removal of dozens of cottages and structures, overhead utilities, and existing infrastructure — including septic tanks discovered mid-construction that required proper pumping and disposal.

Utilities crossed almost every hole, and some properties on site needed to keep service until it could be extended elsewhere, so Aspen worked closely with the developer and subcontractors to sequence removals without disrupting anyone still connected. Record rainfall — as much as 4 to 5 inches in 20 minutes — repeatedly tested the site’s erosion controls during construction and grow-in.

Rather than demolish a spring house built to protect a natural spring on the property, Aspen and the design team incorporated it into the strategy for the new hole — reshaping it to read as an old, abandoned farm structure rather than removing it outright. The spring still flows today with the same water quality it always had.

PROJECT GOALS

  • Construct four new holes and integrate them seamlessly into the existing 18-hole layout.
  • Protect Hoyes Run, a Class Tier II trout stream and one of Maryland’s most sensitive waterways.
  • Coordinate removal of a former theme-town development’s cottages, utilities, and infrastructure before construction.
  • Deliver a course ready for its grand opening despite a first-of-its-kind permitting process in Garrett County.

THE CHALLENGES

  • The first golf course work ever permitted in Garrett County with the Department of the Environment — an unfamiliar process that caused delays.
  • Sediment basins were required to function as finished sub-grade before earthwork was complete, creating conflicts between compliance and construction.
  • Record rainfall — up to 4-5 inches in 20 minutes — repeatedly hammered the site’s erosion and sediment controls.
  • Dozens of cottages, overhead utilities, and undocumented septic systems from a former theme-town development had to be removed before work could begin.

THE RESULTS

  • Every deadline met — the course opened on schedule in June 2008, in great condition for the grand opening.
  • A vegetative buffer strip along Hoyes Run keeps stormwater runoff reaching the trout stream clean.
  • A historic spring house was preserved and reimagined as a scenic feature of the new hole, with the spring’s water quality unchanged.
  • Winner, 2009 Golf Course Industry Affinity Award.

WHAT THE CLUB SAID

The entire team of Aspen did an excellent job with regard to quality — bar none the best I’ve ever seen. As a golf architect and former construction manager and shaper, I recognize high-quality work, and Aspen is the best finishing company in the industry. They are true team players, collaborators, and innovators. They will always be on my bid list.
Todd Schoeder

Golf Architect, Design Workshop

The sequencing on this job was just tremendous. Between all the regulatory agencies and permits for erosion and sediment control, plus coordinating with all the utilities — remember, you can’t control the power company! — it was stunning to me that Aspen brought the project in on time. But they did.
Steve Richards

Owner Representative, DC Development, LLC